Calendar of Events
1st Dec. 1957
The decision to build the Siersza 2 power plant
1st April 1958
The beginning of the construction of the Siersza 2 power plant
30th June 1962
The commissioning of unit 1
30th Nov. 1962
The commissioning of unit 2
1st Jan. 1963
The beginning of the construction-the second stage, units 3 to 6
15th Sept. 1969
The commissioning of unit 3
31st March 1969
The commissioning of unit 4
25th Sept. 1969
The commissioning of unit 5
1st March 1970
The commissioning of unit 6
1990-1994
The modernisation process of units 3 to 6
1993-1996
The modernisation process of the ash removal and slag removal systems
1 April 1996
The transformation of the Siersza power plant into a joint stock company
1997-1998
The construction of the sulfur removal system - "IOS"
30th June 1998
The commissioning of the sulfur removal system - "IOS"of units 3 to 6
1st Jan. 1999
The beginning of the revitalisation process of units 1 and 2
1st Dec. 2000
Obtaining the Certificate of Recognition ISO 14001
29th Dec. 2000
Given to the Południowy Koncern Energetyczny (the Southern Electric Conglomerate - joint stock company)
30th June 2001
The commissioning of unit 1 after the revitalisation process
31st Dec. 2002
The commissioning of unit 2 after the revitalisation process
2003-2004
The modernisation process of the water treatment plant
The decision to build the Siersza 2 power plant
1st April 1958
The beginning of the construction of the Siersza 2 power plant
30th June 1962
The commissioning of unit 1
30th Nov. 1962
The commissioning of unit 2
1st Jan. 1963
The beginning of the construction-the second stage, units 3 to 6
15th Sept. 1969
The commissioning of unit 3
31st March 1969
The commissioning of unit 4
25th Sept. 1969
The commissioning of unit 5
1st March 1970
The commissioning of unit 6
1990-1994
The modernisation process of units 3 to 6
1993-1996
The modernisation process of the ash removal and slag removal systems
1 April 1996
The transformation of the Siersza power plant into a joint stock company
1997-1998
The construction of the sulfur removal system - "IOS"
30th June 1998
The commissioning of the sulfur removal system - "IOS"of units 3 to 6
1st Jan. 1999
The beginning of the revitalisation process of units 1 and 2
1st Dec. 2000
Obtaining the Certificate of Recognition ISO 14001
29th Dec. 2000
Given to the Południowy Koncern Energetyczny (the Southern Electric Conglomerate - joint stock company)
30th June 2001
The commissioning of unit 1 after the revitalisation process
31st Dec. 2002
The commissioning of unit 2 after the revitalisation process
2003-2004
The modernisation process of the water treatment plant