Calendar of Events

1st Dec. 1957
The decision to build the Siersza 2 power plant

1st April 1958
The beginning of the construction of the Siersza 2 power plant

30th June 1962
The commissioning of unit 1

30th Nov. 1962
The commissioning of unit 2

1st Jan. 1963
The beginning of the construction-the second stage, units 3 to 6

15th Sept. 1969
The commissioning of unit 3

31st March 1969
The commissioning of unit 4

25th Sept. 1969
The commissioning of unit 5

1st March 1970
The commissioning of unit 6

1990-1994
The modernisation process of units 3 to 6

1993-1996
The modernisation process of the ash removal and slag removal systems

1 April 1996
The transformation of the Siersza power plant into a joint stock company

1997-1998
The construction of the sulfur removal system - "IOS"

30th June 1998
The commissioning of the sulfur removal system - "IOS"of units 3 to 6

1st Jan. 1999
The beginning of the revitalisation process of units 1 and 2

1st Dec. 2000
Obtaining the Certificate of Recognition ISO 14001

29th Dec. 2000
Given to the Południowy Koncern Energetyczny (the Southern Electric Conglomerate - joint stock company)

30th June 2001
The commissioning of unit 1 after the revitalisation process

31st Dec. 2002
The commissioning of unit 2 after the revitalisation process

2003-2004
The modernisation process of the water treatment plant
Project and implementation Agencja Interaktywna WMC
TAURON Wytwarzanie Spółka Akcyjna prowadzi stronę internetową pod adresem www.pke.pl
TAURON Wytwarzanie Spółka Akcyjna prowadzi stronę internetową Biuletynu Informacji Publicznej: www.bip.pke.pl
32-541 Trzebinia, woj. małopolskie;

tel. 32 71 17 219; informacja 7.00 - 15.00