The dynamic industrial development in Chrzanowska Ziemia (the Chrzanowski Voivodship) at the beginning of the 20th century resulted in an increasing demand for electric power. In 1913 thanks to Polish and French capital the Siersza hydroelectric power plant (5Mw) was built. The maximal power reached in 1928 was 22.5 MW. These were the beginnings of the power plant whose tradition is continued by the Siersza power plant.

The rich coal layers of the nearby Siersza Coal Mine and very good conditions for extracting the coal gave the opportunity to build a new modern thermal power station in Poland in the 50s. In 1962 after the first stage of building the plant two power units started to function of the target installed power of 130 MW each. The main supplier of the equipment was French companies. The second stage of the construction resulted in four power units of the power of 120 MW each. The investment, the so called Polish stage, was finished in 1970. Boilers (for the plant's use) were produced in RAFAKO, Racibórz, turbines in ZAMECH, Elbląg and generators in DOLMEL, Wrocław.
 
After much required modernisation and revitalisation processes of power units 1 and 2 the Siersza power plant gained the power of 813 MW, yet the installed thermal power of 61.3 MWt. The power plant gives the electric power to the domestic electric network of the voltage of 110 and 120 kV and the thermal power to supply nearby housing estates and its own facilities (for its own purposes).
 
As a result of the reconstruction of the 29th December 2000 the Siersza power plant was merged with Południowy Koncern Energetyczny S.A. (the Southern Electric Conglomerate - joint stock company), becoming its branch.
 
Calendar of Events
1st Dec. 1957 The decision to build the Siersza 2 power plant
1st April 1958 The beginning of the construction of the Siersza 2 power plant
30th June 1962 The commissioning of unit 1
30th Nov. 1962 The commissioning of unit 2
1st Jan. 1963 The beginning of the construction-the second stage, units 3 to 6
15th Sept. 1969 The commissioning of unit 3
31st March 1969 The commissioning of unit 4
25th Sept. 1969 The commissioning of unit 5
1st March 1970 The commissioning of unit 6
1990-1994 The modernisation process of units 3 to 6
1993-1996 The modernisation process of the ash removal and slag removal systems
1 April 1996 The transformation of the Siersza power plant into a joint stock company
1997-1998 The construction of the sulfur removal system - "IOS"
30th June 1998 The commissioning of the sulfur removal system - "IOS"of units 3 to 6
1st Jan. 1999 The beginning of the revitalisation process of units 1 and 2
1st Dec. 2000 Obtaining the Certificate of Recognition ISO 14001
29th Dec. 2000 Given to the Południowy Koncern Energetyczny (the Southern Electric Conglomerate - joint stock company)
30th June 2001 The commissioning of unit 1 after the revitalisation process
31st Dec. 2002 The commissioning of unit 2 after the revitalisation process
2003-2004 The modernisation process of the water treatment plant
   
 



           
Project and implementation Agencja Interaktywna WMC
TAURON Wytwarzanie Spółka Akcyjna prowadzi stronę internetową pod adresem www.pke.pl.
TAURON Wytwarzanie Spółka Akcyjna prowadzi stronę internetową Biuletynu Informacji Publicznej: www.bip.pke.pl.
32-541 Trzebinia, woj. małopolskie;
tel. 32 71 17 219; informacja 7.00 - 15.00